The Cougar þ@TheDailyCougar 1m1 minute ago
UH has spent $10M more in student fees on TDECU Stadium than originally planned.
0 replies 0 retweets 0 favorites
7m7 minutes ago
Stadium is under a state of substantial completion, not fully finished. Current costs add up to $3,000 a seat.
0 replies 0 retweets 0 favorites
13m13 minutes ago
Carlucci: 19 months of construction was originally intended for TDECU Stadium.
0 replies 1 retweet 1 favorite
16m16 minutes ago
UH CFO Carl Carlucci now presenting to SGA on behalf of the Department of Administration and Finance.
UH has spent $10M more in student fees on TDECU Stadium than originally planned.
0 replies 0 retweets 0 favorites
7m7 minutes ago
Stadium is under a state of substantial completion, not fully finished. Current costs add up to $3,000 a seat.
0 replies 0 retweets 0 favorites
13m13 minutes ago
Carlucci: 19 months of construction was originally intended for TDECU Stadium.
0 replies 1 retweet 1 favorite
16m16 minutes ago
UH CFO Carl Carlucci now presenting to SGA on behalf of the Department of Administration and Finance.